Industrial & Energy · Lagos, Nigeria
Shutdown cleaning support for a gas processing plant
Confined-space and high-level cleaning delivered inside a 21-day turnaround window.
- Engagement
- Planned turnaround
- Peak crew
- 140
- Window
- 21 days
- Man-hours
- 38,000
Measured outcomes
Contract KPI data, verified through the monthly reporting process.
- Recordable incidents
- 0
- Tasks completed in window
- 100%
- Man-hours worked
- 38,000
The challenge
The operator needed vessel and tank cleaning completed inside a fixed shutdown window with zero recordable incidents.
Approach
- 01
Permit integration
Supervisors trained as permit receivers within the client's permit-to-work system.
- 02
Confined-space teams
Certified entry teams with gas monitoring and standby rescue on every entry.
Mobilisation
Weeks −10 to −2
Task planning, method statements, crew certification
Days 1 to 21
Shutdown execution with daily progress reporting
Discuss a comparable contract.