Skip to content
Cleanora

Healthcare & Hospitals · Doha, Qatar

Rebuilding the clinical cleaning programme for a 1,200-bed tertiary hospital

Consolidating three contractors into one clinical cleaning, porterage and waste contract, mobilised in 28 days.

Contract term
5 years + 2
Workforce
640 FTE
Floor area
310,000 m²
Services
Clinical cleaning, porterage, waste

Measured outcomes

Contract KPI data, verified through the monthly reporting process.

Very-high-risk audit score
99.4%from 82%
Full mobilisation
28 days
Reactive call volume
−31%
Staff competency sign-off
100%

The challenge

Cleaning, porterage and waste were split across three contractors with separate specifications and no common audit regime. Infection-control audits in very-high-risk areas were averaging 82%.

The hospital required a single contractor to take over all three services without disruption to clinical operations.

Approach

  1. 01

    Specification by functional risk

    Every area was re-rated with the IPC team and assigned frequencies, methods and audit thresholds by risk category.

  2. 02

    Workforce transfer

    Incumbent staff were transferred, re-vetted and re-trained to a single clinical competency framework.

  3. 03

    Joint audit regime

    Weekly joint audits with IPC in very-high-risk areas; monthly independent audits elsewhere.

  4. 04

    Rapid response

    A 24/7 rapid response and outbreak team was established with a 20-minute attendance target.

Mobilisation

  1. Days −28 to −14

    Risk re-rating, workforce data review, recruitment of supervisors

  2. Days −14 to 0

    Vetting, clinical competency training, equipment colour-coding

  3. Days 1 to 30

    Baseline audits, daily IPC liaison, rapid response team live

  4. Days 31 to 90

    Corrective actions closed, mobilisation close-out report issued

Client reference

“We moved from three suppliers and three sets of reports to one contract manager and one audit regime. Audit results have been stable above target since month four.”
Director of Support Services, Government tertiary hospital